Dec 29 - Started home search
Jan 27 - Listed townhouse for sale
Jan 30 – We
were notified about the release of new floor plans (Milan and Venice)
Feb 3 –
Signed contract to sell townhouse
Feb 5 –
Decided not to go with Milan because morning room option was not available to
build on any lot
Feb 6 –
Notified that Ryan Homes found 1 site that can fit a Milan model with a morning
room
Feb 6 –
Townhouse inspection
Feb 9 –
Drove to Stephenson, VA to see Milan model
Feb 10 –
Decided to go with the Milan model and build in PS: estimated completion date Sept 1 2015
Feb 13 –
Finance meeting with NVR Mortgage
Feb 15 – Met
with Ryan Homes to finalize colors for home exterior, granite, and cabinets
Feb 16 –
Design center meeting TAC Ceramic
Feb 19 –
Asked TAC for final pricing and asked to add shelves to shower
Mar 2 –
Meeting with Guardian to discuss wiring
Mar 4 – Received TAC pricing info
Mar 23 –
Closed on the townhouse/Moved in with family
May 21 – Told our move in date has been pushed back to Oct 9, 2015
Jun 1 –
Re-visit to TAC to double-check selections; made changes to back splash
Jun 11 –
Notified that we need to schedule our pre-construction meeting; scheduled for
June 26th
Jun 26 - Pre-construction Meeting with PM and sales rep
Jul 9 - BROKE GROUND!
Aug 24 - Pre-Drywall Walk Through
Sep 23 - Received appraisal
Oct 22 - Pre-Settlement Walk Through
Oct 26 - CLOSING!!!
Jul 9 - BROKE GROUND!
Aug 24 - Pre-Drywall Walk Through
Sep 23 - Received appraisal
Oct 22 - Pre-Settlement Walk Through
Oct 26 - CLOSING!!!