There's A Hole In Our Yard!



Finally, they break ground and begin building our home. We texted the PM to get an update because we were told they would break ground on July 6th, but they didn't. Coincidentally, the PM was at the site breaking ground at the time of the text and was nice enough to send pictures of his progress as well as provide us information of the next steps. He informed us that they should be prepping and pouring footings for the foundation walls today and pouring basement foundation walls next week. Then they'll install the underground plumbing, run and tie-in water/sewer, and the next step would be pouring the basement and garage slabs. Its all very exciting!!




We were able to talk with PS and convince them to throw in the wet bar rough-in without us providing any documentation because it was already promised to us by the manager. The manager confirmed the conversation he had with us and we signed the change order form which added the rough-in for FREE!